Free Construction Change Order Request Template Editable Word Document

A change order request that’s easy to approve: what changed and why, a cost breakdown with overhead and profit, the new contract sum and completion date, backup, and signatures for both sides.

2 pages39 KBNo branding — add your company name
Download Free Change Order Template ↓
Page 1 of the change order request template, shown filled in with a made-up example

What’s included

  • Your letterhead: a logo box and company details, then COR number, date, project, contract number, who it’s to and from, and what triggered it.
  • Description and reason: what changed and where, with checkboxes for owner request, design change or RFI, unforeseen condition, code or inspector.
  • Cost breakdown: labor, materials, equipment and subcontractors with their basis, subtotal, overhead and profit, bond, and the total for this change.
  • Contract sum and time: original contract sum, approved change orders to date, this change and the new contract sum, plus days added and the new completion date.
  • Attachments: checkboxes for quotes, labor backup, photos and the directive or RFI.
  • Approval: approved, approved as noted or rejected, with signature blocks for you and the owner or GC.

How to use this template

  1. Fill in the COR number, the project and who it’s going to.
  2. Name exactly what triggered the change (RFI, directive, drawing revision or field condition) and the date.
  3. Describe the changed work and how it differs from your contract.
  4. Price each cost line with its basis, and apply markup only as your contract allows.
  5. Update the contract sum and the days added. Every CO should show the new total.
  6. Attach your backup, send it the way your contract requires, and start the work only after written approval.

Template preview

Shown filled in with a made-up example, so you can see what a finished one looks like. The download is blank and ready for your logo. Tap to enlarge. Open the filled-in example (PDF) →

Page 1 of the change order request template, shown filled in with a made-up examplePage 2 of the change order request template, shown filled in with a made-up example

Get your free template

Enter your email and the download starts right away. No account, no password.

You’ll get the download right away. We only email you updates if you check the box. Privacy

Learning Center

How to document construction change orders

Extra work can become an expensive dispute when the instructions, costs and approvals are scattered across email and field notes. Here is a practical documentation workflow.

Excel tool · $67

Contractor Profit Tracker

An Excel system for one commercial construction project. Tracks change orders, extra work, costs, billing and cash. Every Monday it tells you who to call and where your money is.